Why this exists. UAE practice splits design and supervision into two separate commissions with different billing rhythms. No calculator anywhere models that, so every online estimate is structurally wrong.
Everything here is calculated in your browser. Your numbers are never sent anywhere, stored or seen by us.
- Construction value
- AED 2,500,000
- Construction cost per sq ft
- AED 500
- Design fee at 6.00%
- AED 150,000
- Supervision fee at 2.00%
- AED 50,000
- Supervision billed monthlyOver 14 months
- AED 3,571 / month
- Dubai Municipality construction permitStatutory rate of AED 0.30 per sq ft of building area
- AED 1,500
- DEWA connection chargeOn 120 kW connected load, including VAT and the knowledge and innovation dirhams
- AED 31,520
| Milestone | Share | Payment |
|---|---|---|
| Advance on appointment | 10% | AED 15,000 |
| On completion of initial drawings | 25% | AED 37,500 |
| On completion of performance drawings and authority approval | 35% | AED 52,500 |
| On tender analysis report and execution contract | 30% | AED 45,000 |
Design and supervision are two separate commissions in the UAE. Design is paid on milestones, supervision monthly through construction. The split exists because supervision carries greater liability under the Civil Code.
There is no official UAE fee scale. The Dubai standard consultancy contract leaves every percentage blank for negotiation, so these are observed market rates, not a published tariff.
How this is calculated
- Design milestone percentages are the common market convention. The official Dubai standard form prescribes three design milestones and leaves the percentages open.
- The Dubai Municipality permit fee is the statutory rate under Local Order 3 of 1999, which is per square foot of building area, not a percentage of value. Other authorities charge differently. DDA, for example, charges AED 1.00 per square foot.
- DEWA connection uses the marginal slab table on connected load. Slabs stack like income tax rather than applying a single rate.
- Authority fees are the owner's cost, not the consultant's, under the standard form.
- Civil Defence, telecom and RTA costs are excluded because those authorities publish no usable schedule.
Sources
- Dubai Local Order No. 3 of 1999, Article 10 and Schedule 2
- DEWA connection charges, effective 1 January 2017
This is a planning estimate, not professional advice. Read the full disclaimer.