What an architect costs in Dubai, and what the authorities cost on top
Dubai issued more than ten thousand building permits in a single quarter this year. For a market that active, the quality of publicly available information about what design and approvals actually cost is remarkably poor.
27 August 2026 · 8 minute read
Design and supervision are two different commissions
This is the single most important structural point, and it is written into the Dubai standard form of consultancy contract. Remuneration is expressed as a percentage of the final project cost, of which a stated portion is for design and a stated portion is for supervision.
They are also billed differently. Design is paid against milestones. Supervision is paid in monthly instalments through construction. Treating them as one blended percentage, which most online estimates do, misrepresents both the cash flow and the risk.
The reason for the split is liability. Under the UAE Civil Code, an engineer who both designs and supervises carries joint decennial liability for the building, whereas a design only engineer is liable for design defects alone. Supervision is priced separately because it carries materially more exposure.
Observed fee ranges
| Item | Range |
|---|---|
| Design, multi discipline, standard villa | 5 to 8 per cent of construction value |
| Design, premium villa | 4 to 7 per cent, easing as value rises |
| Construction supervision | 1.5 to 3 per cent, billed monthly |
| Fixed package, compact villa | From about AED 35,000 |
| Fixed package, mid range villa around 5,000 sq ft | About AED 70,000 to 120,000 |
| Fixed package, large luxury villa | About AED 130,000 to 250,000 |
There is no official UAE fee scale, and that can be shown positively rather than assumed: the government's own standard contract leaves every percentage blank for the parties to fill in. Note also that the percentage falls as project value rises, which is economically correct and worth defending in a fee conversation.
The milestone structure
The official standard form prescribes three design milestones, with the percentages left open: on completion of the initial drawings, on completion of the performance drawings and authority approval, and on presentation of the tender analysis report and preparation of the execution contract. Market practice usually adds an advance on appointment.
The fee base ratchets as the project progresses, calculated first on estimated cost, then on the accepted tender amount, then on the actual final cost, with the percentages corrected at each phase. The price of land is excluded from that base.
What the authorities charge
The Municipality's construction works permit fee is set by Local Order No. 3 of 1999, which remains the binding published schedule. It is charged per square foot of total building area, and it does not vary between a villa and a tower.
| Item | Fee |
|---|---|
| Construction works permit | AED 0.30 per square foot of building area |
| Fences | AED 0.10 per linear foot |
| Plan audit, villas | AED 100 |
| Excavation permit, villa | AED 250 |
| Piling and shoring permit | AED 500 |
| Completion certificate field inspection | AED 100 per visit |
| Knowledge and innovation dirhams | AED 20 per transaction |
For scale, an independent international benchmarking study priced a full building permit including all no objection certificates and civil defence approval for a fourteen thousand square foot warehouse in Dubai at just over six thousand dirhams, with the structural inspections during construction carrying no charge at all. That is consistent with the statutory rate and inconsistent with most of the ranges circulating online.
Utility connection is the bigger number
DEWA does not price connections by building type. It uses a marginal slab table on total connected load in kilowatts, applied identically to a villa, a mid rise or a tower, with the slabs stacking like income tax rather than a single rate applying to the whole load. All DEWA no objection certificates are free, and there is no separate drawing review fee. A refundable security deposit of four thousand dirhams applies to a villa.
Floor area, and why nobody can tell you your FAR
There is no published table of floor area ratios by community in Dubai. FAR is a per plot control, issued on that plot's affection plan or in the development control regulations for that development, and both take precedence over any general rule. Every article confidently listing a ratio for a named community is inventing it.
What is published, in the Dubai Building Code, is what counts toward gross floor area. Some of it is counterintuitive:
- Balconies are excluded, whether covered or uncovered. The Code defines a balcony as covered or uncovered, so the blanket exclusion applies to both.
- Parking and parking lobbies are excluded. Basements in villas are excluded, but basements in other buildings are included where habitable.
- Lobbies, corridors and stairs are included.
- A lift shaft counts once, at the recall floor only.
- Structures at roof level must not exceed half the roof area and must sit at least 1.5 m back from the facade, or the whole level counts as a regular floor.
Built up area is a different measurement again, and is always the larger number, because it includes the balconies, parking and projections that gross floor area excludes. Construction cost benchmarks are almost always published per gross floor area, so applying a published rate to a built up area figure overstates the cost by somewhere between six and seventeen per cent.
One change worth knowing about
The standard consultancy contract that has governed this area since 1994 was annulled by Dubai Law No. 14 of 2025, which came into force in 2026 with a one year regularisation window. The new law covers licensing and classification of engineering consultancies and contains no fee provisions and no replacement standard form.
So the fee architecture described here remains the observed market convention and is still what the industry practises. It is simply no longer underpinned by a live regulation, and should be cited as convention rather than as law.
Sources
- Dubai Building Code 2021, Part A
- Dubai Local Order No. 3 of 1999 Regulating Construction Works
- Decree No. 45 of 2021 concerning the Dubai Building Code